given, divided into 5 parts. Part (E) is grammatically correct. Out of the other four parts, one part contains an error. Mark the option containing the part with the error. If none of the parts have errors, mark 'No error' as your answer. Sandra Mwayera wailed as her older (A) / brother slouched next to her in the back (B) / seat of a car - he had died from (C) / cholera as he waited for treatment among (D) /dozens of others outside a hospital. (E)Solution
In C, replace DIED FROM with DIED OF. DIE OF is used when a person dies because of a disease, as in this case, cholera, whereas DIE FROM refers to dying as a result of an external factor such as "dying from bullet wounds" or "dying from falling off a building". Thus, B is the right answer.
A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 50% more efficient t...
In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops w...
- Pipes X and Y can fill a water tank individually in 24 minutes and 36 minutes, respectively. A third pipe Z can empty the tank in 72 minutes. If all three ...
Working together, A and B can do a certain work in 45 days. They work together for 10 days. They complete the remaining work in 28 days with the assista...
A and B can complete a task in 63 days and 42 days, respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will...
Ravi and Manish can do a piece of work in 16 days and 20 days respectively. How long will it take to finish the work if Manish is to be replaced by Sanj...
‘A’ can complete a work in 18 days and is 10% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 15 ...
A and B together, B and C together and A and C together can complete a piece of work in 80 days, 60 days and 70 days respectively. Find the ratio of the...
- An organization engaged 16 workers to complete a task in 24 days. After 9 days, 6 workers had to leave unexpectedly. How many additional days will it now t...
- Time taken by 'X', 'Y' and 'Z' to finish a task is 48 days, 72 days, and 96 days respectively. All started the task together, but 'X' left 12 days before c...