Question
In the following question, a sentence is given, divided
into 5 parts. Part (E) is grammatically correct. Out of the other four parts, only one part is without error. Mark the option containing the part with no error. If none of the parts have errors, mark 'No error' as your answer. If all the parts have errors, marks 'All have errors' as your answer. He interrupted the boss' son's presentation (A) / several times with doubts after doubts (B) / even in the risk of seeming audacious and presumptuous, (C) / only while no one else dared (D)/ to point out the obvious flaws in it. (E)Solution
A- No error. B-replace DOUBTS AFTER DOUBTS with DOUBT AFTER DOUBT. The singular form of DOUBT is grammatically correct; the plural DOUBTS is not followed by words such as AFTER. C - replaced IN with AT. It is an error of preposition. D-replace WHILE with BECAUSE or a synonym of because. WHILE indicates a contradiction between two parts of a sentence, which is not the case here. Here, we need a conjunction to show a cause and effect relationship between the two parts - he interrupted the boss' son's presentation because no one else pointed out the flaws. Thus, words such as because, or its synonyms, are contextually correct. (e) is the right answer.
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after whic...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...
'N,' 'V,' and 'R' have individual work completion times of 140 days, 112 days, and 80 days, respectively. They all started working together on a task, b...
A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
A red JCB machine can complete the excavation of a field in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines...
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed...
A and B together can do a work in 12 days. If A can alone do the same work in 18 days, then in how many days B alone will do the same work?
'Y' is 36% less efficient compared to 'X'. If 'X' requires 86.4 days to finish a task, determine how many days 'Y' will take to complete the same task.
A can complete a work in 12 days and B can complete the same work in 18 days. They work together for 4 days and then B leaves. In how many more days wil...