      Question

      P and Q together can complete some work in 30 days. Q

      and R together can do the same in 24 days. R and P together will take 20 days to complete it. If they all work together, in how many days will the job get done?
      A 25 Correct Answer Incorrect Answer
      B 8 Correct Answer Incorrect Answer
      C 15 Correct Answer Incorrect Answer
      D 16 Correct Answer Incorrect Answer

      Solution

      The correct answer is D