Sam and John can complete a piece of work in 8 days and 12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaini...
A alone can complete 50% of a work in 9 days while B takes 6 days more than A to complete it. If B and C together can complete the work in 12 days, then...
Sohan completes half the work done by Ramesh in 3/4 of the time. If they together can complete the work in 20 days, how much time will Ramesh take to co...
Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constru...
‘D’ alone can finish a job in 50 days, while ‘D’ and ‘E’ together can complete it in 20 days. If ‘E’ worked alone for 22 days and then l...
55 men can complete a piece of work in 18 days. ‘x’ men started the work and after 9 days 64 more men joined them so that whole work was finished in...
- Two pipes, P and Q, can fill a tank in 60 minutes and 100 minutes, respectively. A third pipe R can empty it in 1 hour 40 minutes. Initially, pipes P and R...
A and B together can complete a piece of work in 10 days. B and C together can complete the same work in 12 days, while A and C together can complete it...
- The time taken by ‘X’, ‘Y’ and ‘Z’ to complete a task is ‘6n’ days, ‘9n’ days and ‘12n’ days, respectively. What is the ratio of th...
A ranch has 70 horses, and there’s food to last for 6 days. If 14 more horses are added, then how many days will the food last?