Start learning 50% faster. Sign in now
The man has to first ask a question. Both Q and R are questions for God. But only R can be the first question. The reply is in P. So, it comes after R. Then the next question is Q. Its reply is S. So, the correct sequence is RPQS.
A task can be completed in 15 days when Akash and Bittu work together. Akash is 30% more efficient than Bittu. If both started the task separately and A...
'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency w...
A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in...
Ishan alone can do a certain piece of work in 'w' days and Bhanumati can do it in '2w' days (w is a positive integer). Both together can do the work in ...
A and B alone can complete a work in 15 and 30 days, respectively. 50% of the work is completed by C in 2x days, and the remaining work is completed by ...
A can fabricate a divider in 10 days , while B alone can assemble it in 12 days, If they construct it together and get an installment of Rs 2200, then f...
If 14 men working 9 hours a day can make 24 quilts in 16 days, then in how many days 20 men working 12 hours per day will make 20 quilts?
Pawan can finish a task in 28 days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started wor...
(x + 7) workers finish 60% of a job in 9 days working 4 hours/day. The remaining work is done by (x + 3) workers in 12 days working 3 hours/day. Find x.
‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the ...