Question
An entity sells a factory building held for 20 years.
The legal title transfer occurs on 30 September; economic control passed and risks transferred on 15 September when buyer took possession and started using it. The buyer paid full consideration on 10 October. When should the seller derecognise the building and recognise profit or loss?Solution
Derecognition is when substantially all risks and rewards of ownership are transferred. Economic control transfer (possession/use) on 15 Sep indicates derecognition then, regardless of legal title timing or cash receipt (subject to contract specifics).
A can do a work in 30 hours while B can do it in 20 hours. If C is 60% more efficient than A and B together, then find the time taken by C alone to comp...
A and B together can complete a piece of work in 12 days. B and C together can complete it in 16 days. C and A together can complete it in 24 days. The...
4 girls can do work in 8 days, 3 boys can do the same work in 9 days, 7 men in 2 days, and 5 women in 4 days. Who is the least efficient?
- A group of workers, all equally efficient, were assigned to complete a job in 16 days. However, 10 workers left the job at the end of each day. Despite thi...
Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Det...
P and Q agreed to complete a task for Rs. 6600. P can finish the work alone in 12 days, and Q can complete it alone in 10 days. I...
- Pooja can finish a task by herself in 12 days, while when working together, Manju and Pooja can complete the same task in 6 days. Manju starts the work alo...
A takes 30% longer to complete a task than B. If the total payment for the work is Rs. 11,500 and they complete the task together, how much should A be ...
'Aman' and 'Bhanu' together can complete a work in 7.2 days. Both of them started the work but 'Bhanu' left the work after 3 days and remaining work was...
‘n’ men working 20 hours a day can complete a work in 8 days while (6n – 4) men working 10 hours a day can complete the same work in 8...