A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C...
30 men can complete a task in 160 days. 12 men start the work and manage to do half of it. Then, 18 more men are added to the team to help finish the wo...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
50 men can complete a piece of work in 15 days. 10 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the r...
A can copy 70 pages in 20 hours, A and B together can copy 120 pages in 12 hours. Then in how many pages can B copy 10 hours.
Amit and Binod receive Rs.1400 for work of 7 days. If Amit is 4 times efficient than Binod, then find the daily wage received by Binod.
Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by ...
P and Q together can do a piece of work in 30 days, Q and R together can do it in 20 days. P starts the work and works on it for 5 days, then Q takes it...
'B' and 'C' in a team can complete a piece of work in 25 days and on other hand 'B' alone can do the same work in 40 days. If they started the work in...
Amit is 66(2/3)% more efficient than Vivek who can do the same work in 25% more time than Sameer. If Amit and Sameer together can complete 70% of work ...