Ashish and Anil can do a piece of work in 15 days and 20 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete th...
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed...
- 'Meera', 'Kiran', and 'Suman' together can complete a work in 30 days. 'Meera' and 'Kiran' together can complete the same work in 90 days. 'Suman' alone ca...
- X and Y can complete a piece of work in 20 days. They worked for 10 days and left. Z completed the rest of the work in 10 days. Find how long Z would take ...
Time taken by 'X' and 'Y' to complete a work alone is 72 days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of ...
‘X’ can finish 50% of a job in 8 days. ‘Y’ takes 8 days more than ‘X’ to complete the entire work, and Y is 20% more efficient than ‘Z’....
Time taken by 'A', 'B' and 'C' to complete a work is 51 days, 85 days and 102 days respectively. All of them started the work together but 'B' and 'A' l...
‘A’ alone can complete a work in 20 hours. ‘A’ started the work alone and left after working on it for 15 hours. If ‘B’ completed the rest o...
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
18 men can finish a work in 15 days by working 8 hours a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?