From option 2, Some Refill are Pencils(I) + No Pencil is Pen(E) → Some Refill are not pen(O) → Probable conclusion → Some refill may be pen(I). Hence conclusion I follows. All Refill Are Glitter → Conversion → Some Glitter are Refill (I) + Some Refill are not pen(O) → Probable conclusion → All pen may be glitter(A). Hence conclusion II follows.
‘P’ who is 20% more efficient than ‘Q’ can finish a work in 15 days. ‘P’ and ‘Q’ start working together, but ‘Q’ leaves after 6 days...
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after whic...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850....
Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient tha...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
Anil and Ashish receive Rs.1200 for work of 8 days. If Anil is 5 times efficient than Ashish, then find the daily wage received by Ashish.
‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the wo...
A can complete a piece of work in 10 days. B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many...
Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.