The Securities Appellate Tribunal has rightly ordered the lifting of the trading restrictions imposed on the companies that approached it.
I. Some companies were imposed with trading restrictions.
II. If any company does not approach the Securities Appellate Tribunal, it will be imposed with trading restrictions.
Clearly, from the statement some companies were imposed with trading restrictions which were lifted after those companies approached the Securities Appellate Tribunal. Thus, I is implicit. Not every company needs to approach the Securities Appellate Tribunal. The companies which felt that justice was not being to them with the imposition of the restriction went to the tribunal. The companies which were not restricted earlier need not visit the tribunal. Thus, II is not implicit.
The time taken by ‘A’ to build a wall alone is 20% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percen...
‘A’ alone can complete a work in 20 hours. ‘A’ started the work alone and left after working on it for 15 hours. If ‘B’ completed the rest o...
A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 m...
Ridhi, Sidhi and Tithi can do a piece of work in 30, 45 and 90 days respectively. In how many days can Ridhi do the total work if he is assisted by Sidh...
Numan does 4/ 5 half the work as Gagan in time. If together they take 16 days to complete a piece of work, then how long will Gagan take to complete the...
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, t...
‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...
‘A’ and ‘B’ can do a piece of work in 15 days and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the t...
A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, th...
Anita started working and left after 3 days and aftere that Binita started the rest work and finished it in another 5 days. Had Anita left the work afte...