Question
Four of the following five are alike in the certain way
based on their seating positions and so form a group. Which is the one that does not belong to that group? Study the following information carefully and answer the questions given below: Ten persons are sitting in two parallel rows containing five persons each, in such a way that there is an equal distance between adjacent persons. In row 1, F, G, H, I and J are seated and all of them are facing south. In row 2, K, L, M,N and O are seated and all of them are facing north. Therefore, in the given seating arrangement, each member seated in a row faces another member of the other row. Moreover, each of them reads different newspaper, viz. TOI, Hindustan Times, Economic Times, Dainik Jagran, Punjab Kesari, Amar Ujala, The Hindu, Dainik Bhaskar, Lokmat and Rajasthan Patrika, but not necessarily in the same order. Only two persons sit between J and the one who reads TOI, who sits at an extreme end. K, who sits in the middle of the row, is not an immediate neighbour of L, who does not read Rajasthan Patrika. O sit at an extreme end. J, who reads Punjab Kesari, sits on the immediate right of the one who reads Hindustan Times and J faces the immediate neighbour of L. G does not sit at the extreme left end of his row. K does not read Lokmat. Only one person sits between H and I, I reads TOI. N reads Amar Ujala and is an immediate neighbour of the one who reads Rajasthan Patrika and doesn’t face the person who reads Economic Times. M, who reads Dainik Jagran, is an immediate neighbour of the one who reads Lokmat, who is facing an immediate neighbour of the one who reads Punjab Kesari. Only two persons sit between the one who reads The Hindu and the one who reads Economic Times. G does not read The Hindu. O who does not read Dainik Bhaskar.Solution
'Aman' and 'Bhanu' together can complete a work in 7.2 days. Both of them started the work but 'Bhanu' left the work after 3 days and remaining work was...
βRβ and βSβ can complete an assignment in 72 days and 90 days respectively while βRβ, βSβ and βTβ together can complete the same ass...
A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days....
A task can be completed in 10 days by a team of 6 men and 8 boys. The same task can also be completed in 2 days by 26 men and 48 boys. How long will it ...
A and B together, B and C together and A and C together can complete a piece of work in 10 days, 14 days and 18 days respectively. Find the ratio...
A man, a woman and a boy can do a work in 4, 8, 32 days respectively. How many boys are required with 1 man and 1 woman to complete the same work in 1/4...
20 men or 40 women can complete a piece of work in 24 days. A man and a woman together complete the work and receive a total wage of Rs. 12,000. Find th...
Pβs 3 days work is equal to Qβs 5 days work. If P and Q together can complete the work in 24 days then how much time Q will take to complete 75% of ...
Person 'A' can finish a task in 16 days by working alone. Person 'B', who is twice as efficient as 'A', works on the task alone for 3 days. After that,...
A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count ...