Question
How many persons live below D (in the same type of
flat)? Answer the questions based on the information given below. Ten persons (D, E, F, G, H, I, J, K, L and M) live on 10 different flats of a 5 storey building, where the bottommost floor is 1 and the floor above is 2 and so on. There are 2 types of flats on each floor, flat A and flat B such that flat A is in the west of flat B. Flat A of floor 1 is immediately below of flat A of floor 2, which is immediately below of flat A of floor 3 and so on, similarly for flat B. The dimensions of each of the flats are same. G lives three floors above K in the same type of flat. E lives south east of M. L lives somewhere to the south west of G. F lives to the north east of D. H lives immediately below L in the same type of flat but not to the south west of K. J lives two floors above M in the same type of flat.Solution
1. G lives three floors above K. G and K lives in same flat. 2. L lives somewhere to the south west of G. 3. H lives immediately below L but not to the south west of K.H and L lives in same flat. So, G lives in flat B. G lives on either floor 4 or floor 5. Case I: G lives on floor 4: 4. J lives two floors above M. 5. E lives south east of M, this is not possible in case I(a) and case II, so case I(a), case II(a) and case II(b) are rejected. So, J lives on floor 5 of flat A. M lives on floor 3 of flat A. E lives on floor 2 of flat B
7. F lives to the north east of D.M and J lives in same flat. So, D lives on floor 4 of flat A. F lives on floor 5 of flat B. I lives on floor 3 of flat B. The final table is given below:
βAβ alone can complete a work in 50 hours. βAβ started the work alone and left after working on it for 10 hours. If βBβ completed the rest o...
40 tailors can stitch a batch of dresses in 30 days. If 20 tailors started the job and after 15 days βuβ more tailors joined them such that the rema...
A can complete a piece of work in 10 days and B can complete it in 15 days. They start working together, but B leaves after 3 days. In how many more day...
- An organization engaged 16 workers to complete a task in 24 days. After 9 days, 6 workers had to leave unexpectedly. How many additional days will it now t...
A contractor planned to complete a project in 5 days by employing βaβ workers. But every day exactly 15 workers were absent. As a result, the work g...
Arjun and Sameer can complete a job in 20 days and 25 days respectively. When Arjun, Sameer, and Nikhil work together, they finish it inΒ
M, N and O can complete a task in βtβ, 100, and βt + 20β days respectively. All three started together, but after 15 days, N dropped out. Then, ...
(x + 7) workers finish 60% of a job in 9 days working 4 hours/day. The remaining work is done by (x + 3) workers in 12 days working 3 hours/day. Find x.
A work can be completed by βAβ and βBβ, alone in 10 days and 12 days, respectively. Find the number of days taken by βCβ to complete the sam...
A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x β 2) units per day. They work together for 9 days and ...