Question
How many persons live below D (in the same type of
flat)? Answer the questions based on the information given below. Ten persons (D, E, F, G, H, I, J, K, L and M) live on 10 different flats of a 5 storey building, where the bottommost floor is 1 and the floor above is 2 and so on. There are 2 types of flats on each floor, flat A and flat B such that flat A is in the west of flat B. Flat A of floor 1 is immediately below of flat A of floor 2, which is immediately below of flat A of floor 3 and so on, similarly for flat B. The dimensions of each of the flats are same. G lives three floors above K in the same type of flat. E lives south east of M. L lives somewhere to the south west of G. F lives to the north east of D. H lives immediately below L in the same type of flat but not to the south west of K. J lives two floors above M in the same type of flat.Solution
1. G lives three floors above K. G and K lives in same flat. 2. L lives somewhere to the south west of G. 3. H lives immediately below L but not to the south west of K.H and L lives in same flat. So, G lives in flat B. G lives on either floor 4 or floor 5. Case I: G lives on floor 4: 4. J lives two floors above M. 5. E lives south east of M, this is not possible in case I(a) and case II, so case I(a), case II(a) and case II(b) are rejected. So, J lives on floor 5 of flat A. M lives on floor 3 of flat A. E lives on floor 2 of flat B
7. F lives to the north east of D.M and J lives in same flat. So, D lives on floor 4 of flat A. F lives on floor 5 of flat B. I lives on floor 3 of flat B. The final table is given below:
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
- Person A is twice as efficient as Person B. Person B can complete a certain task in 32 days, while Person C takes 4 days more than Person A to finish the s...
‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and...
Person A is 80% more efficient than person B. A and B together can complete a certain task in 10 days, while B and C together can complete the same task...
'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work w...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
- Ritu completes 50% of a project in 25 days, while Sheetal completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to f...
X can do a piece of work in 22 days. He worked at it for 11 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?