Question
How many persons live towards the north of
Bhawna? Study the following information carefully and answer the question given below: Eight persons Nikita, Amit, Yogita, Priya, Aman, Garima, Shreya and Bhawna lives on a four storey building where as the bottom most floor is numbered as 1 and the top most floor is numbered as 4 but not necessarily in the same order. Each floor has two flats X and Y. Flat X is west of Flat Y of each floor. Flat X of 2nd floor is immediately above the flat X of 1st floor and immediately below the flat X of3rd floor and similarly flat Y of 2nd floor is immediately above the flat Y of 1st floor and immediately below the flat Y of 3rd floor and so on. Aman lives two floors below of Garima. Nikita lives west of Aman. Shreya lives either immediately above or immediately below of Nikita in the same type of flat. Both Yogita and Bhawna live on the same floor. Garima and Yogita are not living on adjacent floors. Priya doesn’t live above the floor on which Shreya lives. Yogita doesn’t live south and north of Priya. Both Amit and Bhawna don’t live in different type of flat.Solution
Again we have, Both Yogita and Bhawna live on the same floor. Priya does not live above the floor on which Shreya lives.
A and B can finish a job in 10 and 15 days respectively. They start together, but after 2 days A leaves. How many more days will B take to complete the ...
‘E’ alone completes a task in 28 days. ‘F’ is 10% less efficient than ‘E’. They worked together for 7 days and then ‘E’ stopped. What pe...
Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion ...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the r...
Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constru...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
P’s 5 days work is equal to Q’s 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 80% of ...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
A’ and ‘B’ together can complete a work in 20 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 60% more efficient t...