Question
I, J, K, L, Y, and Z live on six different floors of the
same building. The lowermost floor in the building is numbered 1, the floor above it is numbered 2, and so on till the topmost floor is numbered 6. I lives on floor numbered 5. L lives on a floor above I. Only K lives below Y. Z lives on an even-numbered floor. How many people live below J? ÂSolution
1. Â Â I lives on floor 5.
→ So, I = 5 2.   L lives on a floor above I.
→ So, L can be on floor 6 only (since floor 5 is already taken by I) 3.   Only K lives below Y.
→ This means: o   K is the only person living on a floor lower than Y o   So, Y must be higher than K, and everyone else must be either above Y or between Y and K 4.   Z lives on an even-numbered floor.
→ So Z can be on floor 2 , 4 , or 6
→ But L is already on 6 (from clue 2), so Z can be on 2 or 4 ·   From clue 1 and 2: o  I = 5 , L = 6 ·   Assume K is on floor 1 (lowest possible) ·   Since only K lives below Y, that means Y must be on floor 2 So: K = 1 , Y = 2 ·   That leaves floors 3 and 4 (and Z must be on an even floor).
So Z must be on floor 4
Z = 4 ·   We now only have floor 3 left for J
J = 3 Final arrangemnt: How many people live below J? • People below J are: Y (floor 2) and K (floor 1) • So, 2 people live below J
A and B can complete a work together in 25 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
- X and Y can complete a task together in 24 days, while Y alone takes 48 days to finish it. X worked alone for some days and then Y completed the rest of th...
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.
A can complete a work in 12 days, and B can complete the same work in 18 days. How many days will they take to complete the work if they work together?
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
A and B together, B and C together and A and C together can complete a piece of work in 10 days, 14 days and 18 days respectively. Find the ratio...
- ‘P’ and ‘Q’ together can finish a task in 15 days while ‘Q’ alone can do it in 25 days. If the ratio of efficiencies of ‘P’ and ‘R’ is ...
Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after 5 ...
- 'Rahul', 'Amit', and 'Vikram' together can complete a work in 20 days. 'Rahul' and 'Amit' together can complete the same work in 60 days. 'Vikram' alone ca...