Question
Statements: Z > L = I ≥ X = W > K = P, P < N = J
Conclusions: I. X > J II. J > K III. P ≤ L In the following question, the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the statements carefully and mark your answer accordingly.Solution
X = W > K = P < N = J                     No relationship can be established between X and J. Hence conclusion I is not true. K = P < N = J                                   J > K. Hence conclusion II is true. L = I ≥ X = W > K = P                       L > P. Hence conclusion III is not true.
‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 12 days and after that ‘N’ is replaced by ‘M’. If the ...
‘P’ can complete 80% of a task in 32 days and ‘Q’ can do 60% of the task in 54 days. If ‘P’, ‘Q’, and ‘R’ all work together, they ca...
Aman is twice as efficient as Suman. Both of them began working together, but Aman stopped after 12 days. Suman then finished the remaining work in 4 da...
Arjun, Binny, and Chiku can collaborate to finish a particular task in 12 days. Additionally, Arjun and Binny working together can complete the task in ...
'A' alone can do some work in 15 days. 'B' is 40% more efficient than 'A'. 'A' worked alone for 8 days and left. How much time (in days) does 'B' need t...
Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu j...
A takes 24 hours more than B to complete the work, and 32 hours more than C to complete the same work. The combined time taken by A and B to finish the ...
P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days wi...
25 men can complete a piece of work in 30 days. ‘x’ men started the work and after 24 days 60 more men joined them so that whole work was finished i...
If A can complete a job in 15 days and B can complete the same job in 10 days, and they work together for 4 days before A leaves. How many more days wil...