The series follows the pattern:
60 + 15 × 1 = 75
75 + 15 × 2 = 105
105 + 15 × 3 = 150
150 + 15 × 4 = 210
210 + 15 × 5 = 285
Therefore, 105 should be in place of 101.
Priya, Riya, and Supriya can complete a piece of work individually in (20/3) days, 20 days, and 25 days, respectively. If they work together, how many d...
X and Y together complete a job in 18 days, while Y alone can do it in 30 days. The ratio of efficiencies of X and Z is 4:5 respectively. What is the ra...
Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.
Pawan completes 40% of a task in 6 days. His efficiency is 100% greater than Qureshi's. How many days will it take for both Pawan and Qureshi, working t...
Consider that 'A' and 'B' were collectively paid Rs. 9,000 for a job. Out of this amount, 'B' received Rs. 3,000. If 'B' can finish this task solo in 48...
With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the...
A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days....
Amin, Basha and Cheez can do a piece of work in 90, 40 and 12 days respectively. But they decide. That a single person will work in a day and receive Rs...