Question

A, B and C can complete a work in 15, 20 and 30 days respectively. They all start working together. After 3 days, C leaves. The remaining work is completed by A and B together. In how many total days is the work finished?

A 64/7 days
B 33/7 days
C 54/7 days
D 34/7 days