Question
24 men can complete _______% of the whole work in 12 days
working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _______ days.The values given in which of the following options will fill the blanks in the same order in which is it given to make the above statement true:A. 36, 10B. 50, 8C. 60, 6D. 40, 12Solution
For A:
24 × 12 × 10/ 36% = 30 × 10 × 8/30%
1 = 1
So, A can be the answer.
For B:
24 × 12 × 10/ 50% = 30 × 8 × 8/30%
9 = 10
So, B cannot be the answer.
For C:
24 × 12 × 10/ 60% = 30 × 6 × 8/30%
1 = 1
So, C can be the answer.
For D:
24 × 12 × 10/ 40% = 30 × 12 × 8/30%
3 = 4
So, D cannot be the answer.
Under Per Drop More Crop scheme the gov. provides financial assistance @ __% of the indicative unit cost to Small & Marginal farmers and @___% to other ...
Which one is not true for canola type varieties of Brassica?
According to Planning commission, Indian region is divided into how many agro climatic zones?
Select the most appropriate synonym of the given word.
EXAGGERATE
As compared to main bacterial chromosome, the size of an episome is
Which of the following primary tillage operation is used to invert the soil partially or completely?
What is the protein content of Barley?
What is the name of the improved variety of the national flower Lotus launched by CSIR-National Botanical Research Institute?
ICAR-INDIAN INSTITUTE OF SOYBEAN RESEARCH is located in_______
Deforestation is