      24 men can complete _______% of the whole work in 12 days

      working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _______ days.The values given in which of the following options will fill the blanks in the same order in which is it given to make the above statement true:A. 36, 10B. 50, 8C. 60, 6D. 40, 12
      A Only A Correct Answer Incorrect Answer
      B Only C Correct Answer Incorrect Answer
      C Only B and D Correct Answer Incorrect Answer
      D Only A and C Correct Answer Incorrect Answer
      E Only A, B and C Correct Answer Incorrect Answer

      Solution

      For A:
      24 × 12 × 10/ 36% = 30 × 10 × 8/30%
      1 = 1
      So, A can be the answer.
      For B:
      24 × 12 × 10/ 50% = 30 × 8 × 8/30%
      9 = 10
      So, B cannot be the answer.
      For C:
      24 × 12 × 10/ 60% = 30 × 6 × 8/30%
      1 = 1
      So, C can be the answer.
      For D:
      24 × 12 × 10/ 40% = 30 × 12 × 8/30%
      3 = 4
      So, D cannot be the answer.