Question
24 men can complete _______% of the whole work in 12 days
working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _______ days.The values given in which of the following options will fill the blanks in the same order in which is it given to make the above statement true:A. 36, 10B. 50, 8C. 60, 6D. 40, 12Solution
For A:
24 × 12 × 10/ 36% = 30 × 10 × 8/30%
1 = 1
So, A can be the answer.
For B:
24 × 12 × 10/ 50% = 30 × 8 × 8/30%
9 = 10
So, B cannot be the answer.
For C:
24 × 12 × 10/ 60% = 30 × 6 × 8/30%
1 = 1
So, C can be the answer.
For D:
24 × 12 × 10/ 40% = 30 × 12 × 8/30%
3 = 4
So, D cannot be the answer.
A ________ is a collection of electronics that can operate a port, a bus, or a device.
What is the name of the batch file that is automatically run when MS-DOS is booted?
If (y)x represents a number y in base x, then which of the following numbers is smallest of all ?
Which memory type is most commonly used as primary storage in modern computers?
A compiler is used to convert the following to object code which can be executed
Which of the following is not a input device ?
Collection of hyperlinked documents on the internet forms the ?
What is 'Multitasking' in computing?
Once an image from a digital camera is processed and displayed, it is considered as-
RTOS stands for