Question
"A" can finish a task by himself in 30 days. "B" is
twice as efficient as "C" and three times more efficient than "A". If "A" and "C" begin the task together, after how many days should "B" take over to ensure the task is completed in precisely 11 days?Solution
Let the total work be 60 units. So, efficiency of 'A' = 60 ÷ 30 = 2 units/day So, efficiency of 'B' = 3 X 2 = 6 units/day And efficiency of 'C' = 6 ÷ 2 = 3 units/day Let the number of days for which 'B' worked alone be 'd'. So, (d X 6) + (11 - d) X (2 + 3) = 60 Or, 6d + 55 - 5d = 60 Or, 'd' = 5 So, 'B' worked alone for 5 days So, 'B' should've joined them after (11 - 5) = 6 days
What is the nature of the pH of milk?
When chlorination of dry slaked lime takes place, _________ will form as the main product.
What is the simplest hydrocarbon?
Which of the following statement regarding Rutherford nuclear model is NOT correct?
Which of the following is an example of a colloidal solution?
If water smells bad, then that odor can be removed by adding:
Magnesium has atomic number as 12. Find out its valiancy.
Which of the following elements is a member of the actinoid series?
Which law governs the behavior of ideal gases?
Acid rain is caused due to pollution of the atmosphere by: