Question
‘D’ and ‘E’ together can finish a task in 40 days, while ‘E’ and ‘F’ together can finish the same task in 30 days. ‘D’ and ‘E’ together worked on it for 35 days and then ‘F’ alone completed the remaining work in 10 days. If ‘D’, ‘E’, and ‘F’ started a certain task and worked together till its completion for which they received Rs. 1800 as total wage, then the share of ‘D’ out of the total wage will be:
More Time and work Questions
- 40 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 64 more men joined them so that whole work was finished in the d...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then find the time ...
- In an office, an employee plans to do a work in 15 days with 6 laptops. But after 8 days, he found that only 50% of the work is done with the laptops worki...
- A, B and C together can complete a project in 6 days. A and B together can complete it in 9 days, and B and C together can complete it in 12 days. In how m...
- A and B can do a work in 24 days and 32 days, respectively. If A works on it for ‘x’ days and B works on it for ‘x – 1’ days, then one-third of the work ge...
- "A" can finish a task in 36 days, while "B" can complete it in 45 days. Both start working on the task together, but "A" stops working after "x" days. The ...
- The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed th...
- Three boys can do a work in 15 days where as 6 girls can do in 12days. What will be the time taken to complete the same work by a teacher if the efficiency...
- P’s 3 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 24 days then how much time Q will take to complete 75% of the wor...
- Efficiencies of workers A, B, and C are in the ratio 5:7:8 respectively. If B and C can do the work in 9 days, then in how many days can A and B finish the...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)