Question
‘D’ and ‘E’ together can finish a task in 40 days, while ‘E’ and ‘F’ together can finish the same task in 30 days. ‘D’ and ‘E’ together worked on it for 35 days and then ‘F’ alone completed the remaining work in 10 days. If ‘D’, ‘E’, and ‘F’ started a certain task and worked together till its completion for which they received Rs. 1800 as total wage, then the share of ‘D’ out of the total wage will be:
More Time and work Questions
- A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish it. ...
- Avinash is twice as good as Bhuvanesh and together they can finish a job in 50 days. Bhuvanesh will finish the work alone in how many days?
- ‘m’ painters can paint a house in 60 days. If the crew increased by 25 painters, they could finish in 40 days. What is the value of ‘m’?
- Ankit and Priya together can complete a piece of work in 200 days and 10 minutes, while Priya and Vikas together can complete the same work in 130 days and...
- If 14 men working 14 hours a day can make 14 quilts in 14 days, then in how many days 28 men working 28 hours per day will make 28 quilts?
- 'X' and 'Y' together can complete the work in 15 days. 'Y' alone can complete the work in 25 days. If Z is 25% more efficient than X, find the time taken b...
- P and Q can separately finish the work in 15 days and 25 days respectively. They worked together and P left the work, so Q complete the remaining work in 5...
- Two pipes, P and Q, can fill a tank in 60 minutes and 100 minutes, respectively. A third pipe R can empty it in 1 hour 40 minutes. Initially, pipes P and R...
- Rohit and Mohit began a job together, but after 10 days Rohit left the task. Mohit finished the rest of the job alone in 8 days. Rohit is 40% less efficien...
- ‘C’ and ‘D’ can complete a job in 20 days and 25 days respectively. They completed it together for Rs. 9,000. What will be C’s share?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)