Question
Amrita, working alone, can accomplish her sales target in 15 days, while Varshita, working alone, takes ____ days to complete her sales target. If they collaborate, Amrita and Varshita together can achieve the same target in ___ days. Which set of values from the following options fills the blanks in the same order, making the statement true?
Amrita, working alone, can accomplish her sales target in 15 days, while Varshita, working alone, takes ____ days to complete her sales target. If they collaborate, Amrita and Varshita together can achieve the same target in ___ days. Which set of values from the following options fills the blanks in the same order, making the statement true?
I. 10, 6
II. 11, 6.75
III. 12, (20/3)
More Time and work Questions
- ‘A’ can do a piece of work in 12 days. ‘B’ can do 70% of the same work in 30 days. If they work together for the entire time and get paid Rs.1504, then fin...
- A pipe can fill a tank in 12 hours, while a second pipe can empty it in 18 hours. If both pipes are opened at the same time, how long will it take to fill ...
- ‘A’ and ‘B’ together can complete a work in 16 days, while ‘B’ and ‘C’ together can complete the work in 12 days. If ‘B’ takes 20 days to complete the work...
- 15 men can finish a work in 16 days by working 6 hours a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?
- ‘A’ can complete a work in 20 days and is 20% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 10 days. The remaining wor...
- A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task in...
- Anuj and Bishnu can complete a task together in 24 days, Bishnu and Raj can complete the same task together in 48 days, and Anuj and Raj can finish it in 3...
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 20 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- A does 1/2 work and B does 3/4 work in the same time. Difference between number of days taken by A and B to work alone to complete the work individually is...
- ‘R’ and ‘S’ can complete an assignment in 72 days and 90 days respectively while ‘R’, ‘S’ and ‘T’ together can complete the same assignment in 24 days. Fin...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)