Question
Aβ and βBβ together can complete a work in 18 days
while βAβ takes 36 days to complete the same work alone. If βCβ is 50% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 36 units Efficiency of (A + B) = 36/18 = 2 units/day Efficiency of βAβ = 36/36 = 1 unit/day Therefore, efficiency of βBβ = 2 β 1 = 1 units/day Efficiency of βCβ = 1.5 Γ 1 = 1.5 units/day Required time taken = 36/1.5 = 24 days