Question
A can complete a work in 25 days. B takes 5 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 25 – 5 = 20 days Let the total work = 100 units Efficiency of A = 100/25 = 4 units/day Efficiency of B = 100/20 = 5 units/day Required time taken = 0.90 x 100/(4+5) = 10 days
What technology is utilized by FASTag to facilitate automatic toll payments?
Which of the following cube in the answer figure CANNOT be made based on the unfolded cube in the question figure?
The first Chairman of Finance commission was
Which statement among the following is incorrect regarding the geographical description of Uttarakhand?
RBI Banking Ombudsman Office for Centralised Receipt and Processing Centre is located in ____________.
Who is the author of the book The Golden House?
Consider the following statements:
1. The design of the National Flag was adopted by the Constituent Assembly of India on 22 July 1947.
2....
When is International Labour Day observed?
ऊंट की खाल पर चित्रांकन किस कला शैली की विषेषता है?
Recently Supreme Court approved establishment of some special courts to prosecute criminal cases against legislators within a year. The number of courts...