Question
A can complete a work in 25 days. B takes 5 days less than A to complete the same work. In how many days can both of them together complete 90% of the work together?
More ESIC Part B Questions
- World tribal day is celebrated on _____________ ?
- A business firm has the following details as of 31.03.2023 : •Additional bad debts during the year = ₹ 25,000 •The firm follows a policy of maintaini...
- Traits can be influenced by:
- KBWJ is related to MZZG in a certain way based on the English alphabetical order. In the same way, OXCD is related to QVFA. To which of the following optio...
- Which of the following enzymes is responsible for unwinding the DNA double helix during replication?
- A rectangular piece of copper foil of length 14 cm and area 308 cm2 is folded along its width to form a cylinder such that there is only one layer of coppe...
- Who was appointed as the Director General of the Narcotics Control Bureau on 17 September 2024?
- Find the average of first 18 whole numbers.
- Which of the following books was not written by Amir Khusrau ?
- Who among the following was not a member of the Socialist group in the Congress Party?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)