Question
A can complete a work in 25 days. B takes 5 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 25 – 5 = 20 days Let the total work = 100 units Efficiency of A = 100/25 = 4 units/day Efficiency of B = 100/20 = 5 units/day Required time taken = 0.90 x 100/(4+5) = 10 days
a snowflake schema is a logical arrangement of tables in a multidimensional database such that the entity relationship diagram resembles a snowflake sha...
What is the primary function of Internet Protocol (IP)?
FAT stands for?
Which network layer protocol is responsible for multicasting, where a packet is sent to multiple destinations simultaneously?
Which of the following will occur when we broadcast two packets on the medium at a time?
Which of the following is NOT a common application of recursion?
Which famous algorithm follows a greedy approach for solving the minimum spanning tree problem in a graph?
Write a query to fetch department-wise count of employees sorted by department’s count in ascending order. EmployeeInfo is the table name.
...In a circuit with n nodes, how many independent KCL equations can be written?
Which of the following power plants relies on the fission of uranium atoms to generate heat?