Question
βAβ alone can complete a work in 30 days. βBβ
alone can complete the same work in 40 days. If βAβ and βBβ work together for 6 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 120 units {LCM of 30 and 40} Then, efficiency of βAβ = 120/30 = 4 units/day Efficiency of βBβ = 120/40 = 3 units/day Combined efficiency of βAβ and βBβ = 4 + 3 = 7 units/day Work completed by βAβ and βBβ together in 6 days = 7 Γ 6 = 42 units Remaining work = 120 β 42 = 78 units Time taken by βAβ alone to complete the remaining work = 78/4 = 19.5 days