Question
βAβ alone can complete a work in 30 days. βBβ
alone can complete the same work in 40 days. If βAβ and βBβ work together for 6 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 120 units {LCM of 30 and 40} Then, efficiency of βAβ = 120/30 = 4 units/day Efficiency of βBβ = 120/40 = 3 units/day Combined efficiency of βAβ and βBβ = 4 + 3 = 7 units/day Work completed by βAβ and βBβ together in 6 days = 7 Γ 6 = 42 units Remaining work = 120 β 42 = 78 units Time taken by βAβ alone to complete the remaining work = 78/4 = 19.5 days
According to the WMO, what concentration of CO β was recorded in 2023, representing 151% of pre-industrial levels?
Sh Ajay Kumar Chaudhary who is appointed as a new Executive Director of RBI, was earlier designated as:
What is the total financial outlay of the BHAVYA Scheme?
The AgriSURE fund aims to support high-risk ventures in which sector?
What is the effective import duty on edible oils after the recent government revision?
What is the significance of the heritage train flagged off by Prime Minister Narendra Modi in Gujarat?Β
___________ topped the World's Best Employers 2021 rankings released by Forbes.
Recently Dmitry Muratov recently won the nobel prize under which category?
Silicon Valley Bank has been recently in the news.Who is the CEO of SVB?
By how much did the number of women seafarers increase from 2014 to 2024?