Question
‘A’ alone can do some work in 14 days. ‘B’ and ‘C’ together can do the same work in 12 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by ‘C’ to complete the work alone.
More Time and work Questions
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 12 t...
- A group of 'x' men can finish a job in 46 days. If 8 additional men had joined the group, they could have completed the same job 16 days earlier. Assuming ...
- Ram can produce 5 pots in a day. Rahul is 40% faster than Ram in pot-making. Together, they work for a period of 55 days, resulting in the production of (x...
- P can complete a job in 30 days. Q alone can complete the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How many d...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 18 days. 'A' started the work alone and worked on...
- Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the remaini...
- Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu join...
- 16 men or 24 women can complete a piece of work in 36 days. A man and a woman together complete the work and receive a total wage of Rs. 9,600. Find the di...
- P and Q can complete a work in 16 days and 24 days, respectively. P, Q and R together can complete the work in 8 days. If R get a total wage of Rs. 3360 to...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)