Question
A work can be completed by ‘A’ and ‘B’, alone in 20 days and 15 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 5 days.
More ESIC Part B Questions
- According to Factories act 1948, Every worker who has worked for at least ______ in a year is entitled to annual leave with wages.
- According to this approach, the industrial relations system is a study of institutions of job regulations and the stress is on the substantive and procedur...
- According to 2011 census, what is the annual exponential growth rate in India?
- Out of the given options,which scheme’s objective is to conduct an annual survey at the gram panchayat level to monitor the progress in the development pro...
- Which of the following options should come in place of the question mark (?) in the given series based on the English alphabetical order? BEV, FIR, JMN, N...
- Which accounting equation forms the basis of the balance sheet?
- The digits of a two-digit number ‘N’ are reversed to form a new number ‘M’. If M < N and N – M = 54, then which of the following maybe ‘N’?
- If the radius of the new spherical container is double the radius of the old spherical container, then the ratio of the volume of the new container and the...
- Consider the following statements regarding the Hybrid Annuity Model (HAM): 1. It is a mix of the Engineering, Procurement and Construction (EPC) and Build...
- The average weight of 100 students in a class is 46 kg. The average weights of boys and girls are 50 kg and 40 kg respectively. What is the difference betw...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)