Question

Akhil and Nikhil together can complete a work in 7 days while Nikhil alone takes 14 days to complete 40% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.

A 12 days
B 10 days
C 7 days
D 15 days
E None of these