Question
A alone can complete 50% of a work in 15 days while B
takes 10 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 15/0.5 = 30 days Time taken by B alone to complete the entire work = 30 + 10 = 40 days Let the total work = L.C.M of 30, 40 and 20 = 120 units Then, efficiency of B = (120/40) = 3 units/day Combined efficiency of B and C = (120/20) = 6 units/day So, efficiency of C alone = 6 – 3 = 3 units/day So, time taken by C alone to complete the entire work = (120/3) = 40 days
The lowest common denominator of a test is otherwise called:
Which of the following states was the largest producer of cotton in 2023-24?
The process by which particular homozygous plant varieties can be selected for creating next generations.
Which one of the following pairs is not correctly matched
The important feature of shifting cultivation is ________
The third tier of Panchayat Raj is:
Photosynthetically Active Radiation (PAR) is the portion of the light spectrum accessible for photosynthesis in green plants. What is the range of spect...
How much budget has been allocated for the additional 2 crore houses under PMAY-G for the period 2024-29?
Country which is pioneer in hybrid rice is :
For Rabi marketing season 2024-25, the MSP for Wheat is ____