Question
A alone can complete 50% of a work in 15 days while B
takes 10 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 15/0.5 = 30 days Time taken by B alone to complete the entire work = 30 + 10 = 40 days Let the total work = L.C.M of 30, 40 and 20 = 120 units Then, efficiency of B = (120/40) = 3 units/day Combined efficiency of B and C = (120/20) = 6 units/day So, efficiency of C alone = 6 – 3 = 3 units/day So, time taken by C alone to complete the entire work = (120/3) = 40 days
Which of the following is not a positional number system?
Which software is used to create presentations?
Which of the following map is also known as chorographical map?
What type of memory stores data in a swap file on a hard drive?
Which shortcut is used to switch to the next workbook in Excel?
What does the abbreviation "RAM" stand for?
Which memory type has the fastest access time?
Which device is used to reproduce drawings using pens that are attached to movable arms?Â
Which one of the following represents the binary equivalent of the decimal number 25 ?
Which of the following is NOT a valid IP address format?