Question
‘A’, ‘B’ and ‘C’ can
complete a piece of work in 40 days, 45 days and 36 days, respectively. All of them started the work together but ‘A’ left the work 20 days before completion of the work while ‘C’ left the work 8 days after ‘A’ left the work. Find the approx. time taken to complete the whole work.Solution
Let, total amount of work = 360 units (LCM of 40, 45 and 36) Efficiency of ‘A’ = 360/40 = 9 units/day Efficiency of ‘B’ = 360/45 = 8 units/day Efficiency of ‘C’ = 360/36 = 10 units/day Let, the whole work is completed in ‘x’ days So, ‘A’ worked for ‘x – 20’ days And, ‘C’ worked for x – 20 + 8 = ‘x – 12’ days So, 9(x – 20) + 10(x – 12) + 8 × x = 360 => 27x = 660 => x = 24.44 ≈ 24 days
Which of the following Statements about Multiplier Effect is/are True?
I- When the government spends a rupee, overall income rises by a multiple ...
Consider the following statements regarding Phase II of the Swachh Bharat Mission (Grameen) [SBM (G)]
1) The program will be implemented...
What is the basic difference between Gross NPA and Net NPA?
I- Gross NPA is the total of Bank loans and Net NPA is the total of all kinds of loan...
Which of the following Statements about IREDA is/are True?
I- It is registered as Non-Banking Financial Company (NFBC) with Reserve Bank of India...
When Government expenditure is more than income, through which of the following ways, it does the deficit financing?
(1) From Banks
(2) Fr...
Which of the following statements about Prompt Corrective Action is/are True?
I- Prompt Corrective Action F...
Who among the following is not one of the eligible beneficiaries of PMUY?