Question
‘A’, ‘B’ and ‘C’ can
complete a piece of work in 40 days, 45 days and 36 days, respectively. All of them started the work together but ‘A’ left the work 20 days before completion of the work while ‘C’ left the work 8 days after ‘A’ left the work. Find the approx. time taken to complete the whole work.Solution
Let, total amount of work = 360 units (LCM of 40, 45 and 36) Efficiency of ‘A’ = 360/40 = 9 units/day Efficiency of ‘B’ = 360/45 = 8 units/day Efficiency of ‘C’ = 360/36 = 10 units/day Let, the whole work is completed in ‘x’ days So, ‘A’ worked for ‘x – 20’ days And, ‘C’ worked for x – 20 + 8 = ‘x – 12’ days So, 9(x – 20) + 10(x – 12) + 8 × x = 360 => 27x = 660 => x = 24.44 ≈ 24 days
NaCl has which kind of bonds?
The device that converts AC into DC is:
Which of the following relation is correct?
Why do metals conduct electricity?
Which chemical is also known as carbolic acid?
Which of the following is an example of a heterogeneous mixture?
Which gas is produced due to incomplete combustion of fuel?
Water from soil enters into the root hairs owing to :
Red light is used for signals because it has –
What is the hybridization of carbon in ethyne (Câ‚‚Hâ‚‚)?