Start learning 50% faster. Sign in now
ATQ, For 'Amit': Simple interest = Principal × (Rate/100) × Time period in years = (x - 600) × (10/100) × 4 = 0.4 × (x - 600) = Rs. (0.4x - 240) For 'Bittu': ATQ,
Or, x = 3901.5 × (400/289) So, x = 5400 For 'Chintu': Amount received by 'Chintu' = 3000 × (20/100) × 3 + 3000 = 1800 + 3000 = Rs. 4,800 For option 'A': Amount received by 'Chintu' = 60% of 2800 + 0.6x = 0.6 × 2800 + 0.6 × 5400 = 1680 + 3240 = Rs. 4,920 ≠ Rs. 4,800 So, option 'A' is incorrect For option 'B': Amount received by 'Chintu' = 30% of 7900 + 0.45x = (0.3 × 7900) + (0.45 × 5400) = 2370 + 2430 = Rs. 4,800 Therefore, option 'B' is correct.
P can do a piece of work in 25 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, ...
8 children and 6 women together can complete a piece of work in 10 days and work done by a children in one day is one-third of the work done by a women ...
Anita and Binita have individual completion times for a task; Anita can complete it in 40 days, while Binita can do it in 56 days. Anita initiated the t...
A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after whic...
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project...
'Alex,' 'Ben,' and 'Charlie' can individually complete a task in 40, 60, and 100 days, respectively. They decide to work together, but there's a unique ...
A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task...
Billy, Tony and Mike were three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but ...
A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :