Question
Ms. Riya allocated her savings into three different
funds X, Y, and Z in the ratio 8:7:6. The interest rates for these funds are w% p.a., (w β 4)% p.a., and (w + 4)% p.a., respectively (simple interest). If the total simple interest earned in 1 year is Rs. 3,320 and the interest rate of fund Y compared to Z is in the ratio 3:5, find the total savings invested.Solution
ATQ, Given (w β 4) : (w + 4) = 3 : 5 5(w β 4) = 3(w + 4) 5w β 20 = 3w + 12 2w = 32 w = 16 Rates: X = 16% , Y = 12% , Z = 20% Let investments be: X = 8k, Y = 7k, Z = 6k Total SI for 1 year: SI = [8k16 + 7k12 + 6k*20] / 100 = [128k + 84k + 120k] / 100 = 332k / 100 Given SI = 3320: 332k/100 = 3320 332k = 332000 k = 1000 Total savings = (8 + 7 + 6)k = 21k = 21 * 1000 = 21000 Answer: Total savings invested = Rs. 21,000
P, Q and R can do some work in 11 days, 20 days and 55 days respectively. In how many days can the work be done, if P gets the assistance of Q and R on ...
Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 6 hours a day can complete a task in 15 days, whereas (3n - 2) women working ...
A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 d...
βAβ alone can do some work in 13 days. βBβ and βCβ together can do the same work in 18 days. If βBβ is half as efficient as βAβ, the...
Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
Aman can complete a task in 12 days, while Bhanu alone can complete the same task in 18 days. Aman starts the work alone and continues for 4 days. Then,...
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of e...
Before 'A' joined the team, 'S' and 'V' were alternating days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to fi...
P can do a piece of work in 25 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, ...
Arjun, Bharat and Chintu together can complete a task in 8 days. Bharat is 25% less efficient than Arjun. Arjun and Chintu together can complete the tas...