Question
Below given are 2 wrong number series, where ‘x’ is
the correct replacement of the wrong term of series I & ‘y’ is the correct replacement of the wrong term of series II. Series I: 50, 57, 69, 84, 100, 118 Series II: 213, 109, 111, 168, 348, 843 I. 'y' is not a multiple of 'x'. II. Adding 24 to 'y' and then dividing the result by 'x+9' leaves a remainder of 45. III. The sum of the incorrect values is divisible by 12.Solution
ATQ, Series I 50 + 7 × 1 = 57 57 + 6 × 2 = 69 69 + 5 × 3 = 84 84 + 4 × 4 = 100 100 + 3 × 5 = 115 x = 115 Series II 213 × 0.5 + 2.5 = 109 109× 1 + 2 = 111 111 × 1.5 + 1.5 = 168 168× 2 + 1 = 337 337× 2.5 + 0.5 = 843 ‘y’ = 337 I. y/x = 337/115 (True) II. (y + 24)/(x + 9) = (337 + 24)/(115 + 9) = 361/124 (False) III.118 + 348 = 466 = 466/12 (False) Hence, Only I is correct
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
A painter charges ₹500 for every hour of work. If he works for 6 hours a day and completes a project in 5 days, what is the total amount charged by th...
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, t...
P, Q, and R can complete a work in 12 days. 15 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q a...
- If ‘X’ finishes a project in 24 days whereas ‘X’ and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will ...
"'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to fi...
'A' can complete a certain task in 60 days, while 'B' can do the same in 45 days. 'A' starts the task and works alone for 18 days, after which 'B' joins...
A and B can finish a piece of work in 20 days and 30 days respectively. Both work on alternate days. In how many days will the work be completed when A ...
(x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. F...
A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C ...