Question
Quantity I : Number of days the work is extended beyond normal days. A can do a piece of work in 100 days and B in 60 days. Both of them start working together and 6 days before the scheduled completion, B drops out. Quantity II : Number of days required to complete the work working 10 hrs daily by 60 women working together. 24 men take 20 days working 12 hrs daily to do a piece of work, if 5 women do as much work as 4 men.
More Quantity Inequality Questions
- In the question, two quantities I and II are given. You have to solve both the quantities to establish the correct relation between Quantity-I and Quantity...
- What is the population of village A in 2021? Quantity I: Population of village A in 2020 was 65,000 and it increased by 12% in 2021 over 2020. Quantity II:...
- What is the population of village A in 2021? Quantity I: Population of village A in 2020 was 60,000 and it increased by 15% in 2021 over 2020. Quantity II...
- Quantity I: The rate at which the train must run to reduce the time to 30 minutes. A train takes 40 minutes for a journey if it runs at 72 km/hr. Quantity...
- Consider only numeric value. Quantity I: A number is increased by 25%, and then the result is decreased by 20%. The final number is 540. What was the orig...
- In the following question, read the given statement and compare Quantity I and Quantity II on its basis. (Only quantity is to be considered) (pq + y + 14)1...
- Quantity I : A Alone can complete a work in 21 days. If be alone work for eight days and then leaves, then B alone can complete the remaining work in seve...
- In the question, two Quantities I and II are given. You have to solve both the Quantity to establish the correct relation between Quantity-I and Quantity-I...
- Quantity I: A vessel contains a mixture of milk and water in the ratio of 7 : 5. If 9 litre of mixture is sold and replaced by same amount of water then th...
- Quantity I: An amount is to be distributed among A, B, and C in the ratio 1:3:2 respectively, but was erroneously distributed in the ratio 2:7:9 due to whi...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Both can complete the work in 300/8 = 37.5 days Work done in (37.5 – 6) days = 31.5 × 8 = 252 unit Remaining work = 300 – 252 = 48 unit After B drops out remaining part will be completed by A in = 48/3 = 16 days Total time taken = 31.5 + 16 = 47.5 days Actual time taken = 37.5 days Difference = 47.5 – 37.5 = 10 days Quantity II: 5W = 4M 1W = (4/5) M Let the no. of days required to complete the work is D. 10 × 60W × D = 24M × 20 × 12 10 × (60×4)/5 M × D = 24M × 20 × 12 D= 12 days Hence, Quantity I < Quantity II .