Question
Quantity I : Number of days the work is extended beyond normal days. A can do a piece of work in 100 days and B in 60 days. Both of them start working together and 6 days before the scheduled completion, B drops out. Quantity II : Number of days required to complete the work working 10 hrs daily by 60 women working together. 24 men take 20 days working 12 hrs daily to do a piece of work, if 5 women do as much work as 4 men.
More Quantity Inequality Questions
- Direction: The question consists of two quantities, choose the correct option which represents the correct relation between Q1 and Q2. Quantity (Q1): The...
- Quantity-I: Both 'Asmita' and 'Bittu' can finish a sales target in 48 days and 27 days, respectively. If they begin working together, determine the number ...
- Quantity I: A bag contains 5 red, 7 blue, and 8 green balls. Two balls are drawn randomly. What is the probability that both balls drawn are green? Quantit...
- Quantity I : Distance travelled by the cycle to reach point c from point B if a Bike travels the same distance in 2 hours and the speed of the cycle is 140...
- Aman' and 'Bhuvan' can complete a certain task in 24 days and 40 days, respectively. Both started working together, but 'Bhuvan' left after 5 days. Afterwa...
- At what time will a train reach city P from city Q? Statement I: The 600 meter long train crosses a signal pole in 20 seconds. Statement II: The another ...
- Quantity I: There are two types of animals in a pet shop. Some are puppies and some are kittens. Each kitten takes 8 biscuits and each puppy takes 11 biscu...
- Ratio of perimeter of rectangle and length of rectangle was given - 17:5. Quantity I: then area of square whose side is half of rectangle's perimeter Qua...
- In the question, two Quantities I and II are given. You have to solve both the Quantity to establish the correct relation between Quantity-I and Quantity-I...
- Quantity I. In what time will Rs. 48,000 amount to Rs. 52,920 @ 5% compound interest? Quantity II. In what time will Rs. 50,000 amount to Rs. 53060....
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Both can complete the work in 300/8 = 37.5 days Work done in (37.5 – 6) days = 31.5 × 8 = 252 unit Remaining work = 300 – 252 = 48 unit After B drops out remaining part will be completed by A in = 48/3 = 16 days Total time taken = 31.5 + 16 = 47.5 days Actual time taken = 37.5 days Difference = 47.5 – 37.5 = 10 days Quantity II: 5W = 4M 1W = (4/5) M Let the no. of days required to complete the work is D. 10 × 60W × D = 24M × 20 × 12 10 × (60×4)/5 M × D = 24M × 20 × 12 D= 12 days Hence, Quantity I < Quantity II .