Question

    Quantity I : Number of days the work is extended beyond

    normal days. A can do a piece of work in 100 days and B in 60 days. Both of them start working together and 6 days before the scheduled completion, B drops out. Quantity II : Number of days required to complete the work working 10 hrs daily by 60 women working together. 24 men take 20 days working 12 hrs daily to do a piece of work, if 5 women do as much work as 4 men.
    A Quantity I > Quantity II Correct Answer Incorrect Answer
    B Quantity I < Quantity II Correct Answer Incorrect Answer
    C Quantity I ≥ Quantity II Correct Answer Incorrect Answer
    D Quantity I ≤ Quantity II Correct Answer Incorrect Answer
    E Quantity I = Quantity II or no relation Correct Answer Incorrect Answer

    Solution

    Quantity I: Both can complete the work in 300/8 = 37.5 days Work done in (37.5 – 6) days = 31.5 × 8 = 252 unit Remaining work = 300 – 252 = 48 unit After B drops out remaining part will be completed by A in = 48/3 = 16 days Total time taken = 31.5 + 16 = 47.5 days Actual time taken = 37.5 days Difference = 47.5 – 37.5 = 10 days Quantity II: 5W = 4M 1W = (4/5) M Let the no. of days required to complete the work is D. 10 × 60W × D = 24M × 20 × 12 10 × (60×4)/5 M × D = 24M × 20 × 12 D= 12 days Hence, Quantity I < Quantity II .

    Practice Next

    Relevant for Exams: