Question
Two teams A and B can complete a road construction project in 18 days and 27 days respectively. They start working together, but after some days team B leaves. The project is completed in 15 days in total. For how many days did both teams work together?
More Quant Miscellaneous Questions
- In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between x and y and choose the co...
- A parallelogram has two adjacent angles measuring 110° and 70°. What is the difference of the other two angles?
- 69 73 64 80 ? 91
- The ages of P, Q, and R are in the ratio 2:3:5. After 5 years, the sum of their ages will be 75 years. What are their present ages?
- Three boxes B1, B2, B3 contain red and green balls in the ratio 1:1, 3:5, and 5:3 respectively. A box is selected at random and a ball is drawn. What is th...
- A company’s quarterly sales (in lakh units) are: Q1: 18, Q2: 24, Q3: 21, Q4: 27 Find the percentage increase from Q1 to Q4.
- 13, 55, 111, 183, 273, ?
- The simple interest on a sum of money for 3 years is 1,200 at a rate of 10% per annum. What is the compound interest on the same sum for the same time and ...
- Each question contains a statement followed by Quantity I and II. Read the information clearly and answer your questions accordingly. Quantity I : The ...
- A person spends 40% of his income on rent, 30% on food, and 20% on education. If he saves ₹2000, what is his total income?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)