Question
βPβ who is 20% more efficient than βQβ can
finish a work in 15 days. βPβ and βQβ start working together, but βQβ leaves after 6 days. The remaining work is completed by βPβ alone in βyβ days. Find the value of βyβ.Solution
ATQ,
Time taken by βQβ to complete the work = 1.2 Γ 15 = 18 days
Let the total work be 90 units
Efficiency of βPβ = 90/15 = 6 units/day
Efficiency of βQβ = 90/18 = 5 units/day
Work completed by βPβ and βQβ in 6 days = (6 + 5) Γ 6 = 66 units
Therefore, y = (90 β 66)/6 = 4
If money is neutral,
What was the primary reason for the reduction in India's current account deficit from USD 67 billion in 2022-23 to USD 23.2 billion in 2023-24?
Keynes assumed that the price level was fixed because
According to the Quantity Theory of Money (QTM), what is the predicted effect of a change in the velocity of money on the price level in the long run?
Real Wages = 500, Consumer price index = 1.2. Calculate nominal wages?
In the Solow model, what is the effect of an increase in the saving rate on the long-term growth rate of an economy?
Locus point of Isoquants wherein the marginal productivity of one of the factors is 0 is called
A card is drawn randomly from a deck of ordinary playing cards. You win Rs.100 if the card is a spade or an ace. What is the probability that you will w...
What is the Cash Reserve Ratio (CRR)?
The inverse demand function for a commodity is P = 50-2Q-Q2 . Calculate the consumer surplus when quantity demanded is 5 unts.