Question
A contractor was tasked with constructing a bridge
within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?Solution
Let the contractor employed тАШxтАЩ more workers after 40 days. So according to question: (75 ├Ч 40)/0.75 = {(x + 75) ├Ч 5}/0.25 20x + 1500 = 4000 20x = 2500, x = 125 So, 125 more workers are required to complete the work on time.
рдЕрднреВрддрдкреВрд░реНрд╡ рд╢рдмреНрдж рдХрд╛ рдЕрдВрдЧреНрд░реЗрдЬреА рдкрд░реНрдпрд╛рдп рд╣реИ –
рд░рд╛рдЬрднрд╛рд╖рд╛ рд╕реЗ рд╕рдВрдмрдВрдзрд┐рдд рднрд╛рдЧ-17 рдореЗрдВ рд╡рд░реНрдгрд┐рдд рдЕрдиреБрдЪреНрдЫреЗрдж 210 рдореЗрдВ рдЗрдирдореЗрдВ рд╕я┐╜...
Select the correct Hindi translation of the words given below:
рдирд┐рд░реНрдпрд╛рдд , рдЖрдпрд╛рдд , рд╡реНрдпрд╛рдкрд╛рд░ , рд╡рд╕реНрддреБ┬а
рдиреАрдЪреЗ рджрд┐рдП рдЧрдП рд╢рдмреНрджреЛрдВ рдХрд╛ рд╕рд╣реА рдЕрдВрдЧреНрд░реЗрдЬрд╝реА рдЕрдиреБрд╡рд╛рдж рд╡рд┐рдХрд▓реНрдкреЛрдВ рд╕реЗ рдЪя┐╜...
рд░рд╛рдЬрднрд╛рд╖рд╛ рд╡рд┐рднрд╛рдЧрдХреА рдкрддреНрд░рд┐рдХрд╛ рд░рд╛рдЬрднрд╛рд╖рд╛ рднрд╛рд░рддреА рдХрд╛ рдкреНрд░рдХрд╛рд╢рди рдХрдм рд╣реБрдЖ ?
1955 рдореЗрдВ рдЧрдард┐рдд рд░рд╛рдЬрднрд╛рд╖рд╛ рдЖрдпреЛрдЧ рдХреЗ рдЕрдзреНрдпрдХреНрд╖ рдереЗ ?
рд░рд╛рдЬрднрд╛рд╖рд╛ рд╕рдВрдХрд▓реНрдк рдХрдм рдкрд╛рд░рд┐рдд рд╣реБрдЖ ? -┬а┬а
рд╣рд┐рдиреНрджреА рднрд╛рд╖рд╛ рдХреЛ рдорд╛рдирдХ рд░реВрдк рдкреНрд░рджрд╛рди рдХрд░рдиреЗ рдХрд╛ рдкреНрд░рдпрд╛рд╕ рд╕рд░реНрд╡рдкреНрд░рдердо рдХя┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдореЗрдВ рд╕реЗ credit rationing рдХрд╛ рд╕рд╣реА рдЕрд░реНрде рдЪреБрдирд┐рдПред┬а
рдиреАрдЪреЗ рджрд┐рдП рдЧрдП рд╡рд╛рдХреНрдпреЛрдВ рдХреЗ рд╕рд╣реА рдЕрдиреБрд╡рд╛рдж рдХрд╛ рдорд┐рд▓рд╛рди рдХрд░реЗрдВ рдФрд░ рдЙрдЪрд┐рдд рд╡рд┐я┐╜...