Question
A contractor was tasked with constructing a bridge
within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?Solution
Let the contractor employed тАШxтАЩ more workers after 40 days. So according to question: (75 ├Ч 40)/0.75 = {(x + 75) ├Ч 5}/0.25 20x + 1500 = 4000 20x = 2500, x = 125 So, 125 more workers are required to complete the work on time.
рдЬрд┐рд╕рдХреЗ рд╕рд┐рд░ рдкрд░ рдЪрдиреНрджреНрд░рдорд╛ рд╣реЛ
рдореМрди рдХрд╛ рд╡рд┐рд▓реЛрдо рд╢рдмреНрдж рд╣реИ
2023 рдореЗрдВ рд╡рд┐рд╢реНрд╡ рд╣рд┐рдВрджреА рд╕рдореНрдореЗрд▓рди рдХрд╛ рдЖрдпреЛрдЬрди рдХрд╣рд╛рдВ рдкрд░ рд╣реБрдЖ ?
рдирд┐рдореНрди рдореЗрдВ рдХреМрди рд╕рд╣реА рд╣реИ ?
рдореБрд╕реНрдХреБрд░рд╛рд╣рдЯтАЩ рдХрд┐рд╕ рдкреНрд░рдХрд╛рд░ рдХреА рд╕рдВрдЬреНрдЮрд╛ рдХрд╛ рдЙрджрд╛рд╣рд░рдг рд╣реИ?
рдЕрдореЗрд░рд┐рдХрд╛ рдореЗрдВ рдПрдХ рдмрд╛рд░ ............ рд╣реБрдИ ред рджрд┐рдП рдЧрдП рдЙрдкрдпреБрдХреНрдд рд╢рдмреНрдж рд╕реЗ рд░рд┐рдХреНрдд я┐╜...
рд╕реВрдЪреА 1┬а рдХреЛ рд╕реВрдЪреА 2┬а рд╕реЗ рд╕реБрдореЗрд▓рд┐рдд рдХреАрдЬрд┐рдП рдФрд░ рд╕реВрдЪрд┐рдпреЛрдВ рдХреЗ рдиреАрдЪреЗ рджрд┐рдП рдЧрдП ...
рд╢реБрджреНрдз рд╡рд╛рдХреНрдп рдХреА рдкрд╣рдЪрд╛рди рдХреАрдЬрд┐рдпреЗ┬а
'рдЕрдиреБрддрд╛рди' рдХрд╛ рд╕рдореНрдмрдиреНрдз рд╣реИред
- тАШрдкрд╣рд▓рд╛ рд╕реНрдерд╛рдитАЩ рдореЗрдВ тАШрдкрд╣рд▓рд╛тАЩ рдХрд┐рд╕ рдкреНрд░рдХрд╛рд░ рдХрд╛ рд╡рд┐рд╢реЗрд╖рдг рд╣реИ?