Question
A contractor was tasked with constructing a bridge within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?
More Quant Miscellaneous Questions
- If a = 0.121212… (repeating) and b = √5, state whether each is rational or irrational.
- Person 'X' can complete a task in 30 days when working at full efficiency, while person 'Y' can finish the same task in 50 days at full efficiency. If 'Y' ...
- A train takes 3 hours to travel a certain distance at a speed of 60 km/h. If the speed is increased by 20 km/h, how long will it take to cover the same dis...
- Which of the following scheduling algorithms is designed to reduce the turnaround time and waiting time in a multitasking environment?
- At 9:30 a.m., the length of a pole’s shadow is equal to its height. What is the sun’s altitude at this time?
- A businessman bought goods for Rs 1050 and sold them on the same day for Rs 1228.5 on credit for 10 months, thus earning a profit of 4%. Find the rate of i...
- Solve: 2(x+3) = 8(x–1)
- From a group of 7 men and 4 women, a committee of 4 persons is to be formed. The probability that the committee has at least one woman is:
- What file extension does MS PowerPoint use by default?
- Question 10
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)