Question
Aman and Bhanu, working separately, can complete a task in 32 days and 40 days, respectively. They started working together, but Aman’s efficiency decreased by 40%, while Bhanu’s efficiency increased by 25%. How much time will it take for them to complete the work together under these new conditions?
More Quant Miscellaneous Questions
- In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between x and y and choose the co...
- A car travels from city A to city B at a speed of 60 miles per hour and returns to city A at a speed of 40 miles per hour. If the total round trip takes 5 ...
- In a rectangular floor of length and breadth of 12 metres and 9 metres, respectively, square tiles each of 3 metre edge length are to be laid. If the cost ...
- If f(x) is periodic of period T, then:
- Printer resolution is measured in which of the following?
- The marks (out of 50) of 5 students are: 10, 14, 18, x, 26. The mean is 18. Find x and the standard deviation.
- In Microsoft PowerPoint, which view is the primary mode for creating and editing presentations?
- Suppose Ranjan purchases a bike for Rs. 6,50,000 and sells it for Rs. 8,00,000, calculate the profit % in this transaction.
- Train P takes 24 seconds to pass a tree and 34 seconds to pass through a 150-meter-long tunnel. Train Q, which is 440 meters long, takes 17.6 seconds to pa...
- Determine the area of an equilateral triangular field having perimeter of 42m.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)