Question
A can finish a piece of work in 16 days, B in 20 days,
and C in 24 days. A begins the work, with B joining after 4 days, followed by C joining 2 days later. How many additional days will it take to complete the work?ÂSolution
Let the total work be 1 unit. A’s efficiency = 1/16, B’s efficiency = 1/20, and C’s efficiency = 1/24. A works alone for the first 4 days: Work done by A in 4 days = 4 × 1/16 = 1/4. Remaining work = 1 - 1/4 = 3/4. A and B work together for 2 more days: Work done by A and B in 2 days = (1/16 + 1/20) × 2 = (9/80) × 2 = 9/40. Remaining work = 3/4 - 9/40 = 30/40 - 9/40 = 21/40. Now, A, B, and C are working together. Their combined efficiency = 1/16 + 1/20 + 1/24 = 37/240. Time taken to complete the remaining work = (21/40) ÷ (37/240) = 126/37 ≈ 3.4 days. Final Answer: (b) 3.4 days
2387.56 + ? – 2248.14 = 1765.45 – 1574.23
 15.78% of (287 + 302) + 12³ = ?% of 170 + 8 × 14 + 3²Â
? = (5.8)2 + (8.9)2 + (4.7) 2 + 24.7% of 20
49.99% of 639.99 + 159.98% of 49.99 = ?2
(14.66)2 + (343.84 ÷ 3.88 - 55.87) = ? + 91.23
(18.21)² - (12.9)² = 20% of 649.9 - ? + 400.033
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)
49.96% of 120.21 + √(15) ÷ 1.87 × 4.41 = ?Â
(3/8) × 479.84 + (2/5) × 449.67 = ? × 12.25Â
64.889% of 399.879 + √? = 54.90% of 799.80 – 44.03% of 400.21