📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A can finish a piece of work in 16 days, B in 20 days,

      and C in 24 days. A begins the work, with B joining after 4 days, followed by C joining 2 days later. How many additional days will it take to complete the work? 
      A 5 days Correct Answer Incorrect Answer
      B 3.4 days Correct Answer Incorrect Answer
      C 4.4 days Correct Answer Incorrect Answer
      D 6 days Correct Answer Incorrect Answer
      E 7 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 1 unit. A’s efficiency = 1/16, B’s efficiency = 1/20, and C’s efficiency = 1/24. A works alone for the first 4 days: Work done by A in 4 days = 4 × 1/16 = 1/4. Remaining work = 1 - 1/4 = 3/4. A and B work together for 2 more days: Work done by A and B in 2 days = (1/16 + 1/20) × 2 = (9/80) × 2 = 9/40. Remaining work = 3/4 - 9/40 = 30/40 - 9/40 = 21/40. Now, A, B, and C are working together. Their combined efficiency = 1/16 + 1/20 + 1/24 = 37/240. Time taken to complete the remaining work = (21/40) ÷ (37/240) = 126/37  ≈ 3.4 days. Final Answer: (b) 3.4 days

      Practice Next
      ask-question