Question
βAβ alone can complete a work in 30 days. βBβ
alone can complete the same work in 40 days. If βAβ and βBβ work together for 6 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 120 units {LCM of 30 and 40} Then, efficiency of βAβ = 120/30 = 4 units/day Efficiency of βBβ = 120/40 = 3 units/day Combined efficiency of βAβ and βBβ = 4 + 3 = 7 units/day Work completed by βAβ and βBβ together in 6 days = 7 Γ 6 = 42 units Remaining work = 120 β 42 = 78 units Time taken by βAβ alone to complete the remaining work = 78/4 = 19.5 days
If (x - 1) 3 Β + (y - 2) 3 Β + (z - 3) 3 Β + 3(x + y - 3)(y + z - 5)(x + z - 4) = 0, then what is the value of (x + y +...
In an orchard, the ratio of the number of mango and lichi trees is 9:10, respectively. Also, there are few apple trees in the orchard which is 50% more ...
If x + 1/x = 6, then x2 + 1/x2 is:
If tan x + cot x Β = 7, find Β tan3 x + cot3 xΒ = ?
If polynomial P(x) = x3 - 3x2 + 5x-3 is divided by polynomial G (x) = x2 - 2, the quotient and remainder are:
If x + y + z = 30, xΒ² + YΒ² + zΒ² = 460 and x z = yΒ², then find the value of x z?
Solve: 1/x + 1/y = 5/2 and 1/x β 1/y = 1/6
If 'x' = β5, then find the value of (x - 2)Β² + (x + 2)Β².
If (a + b + c) = 9, find (a – 4)3 + (b – 2)3 + ( c – 3)3 - 3(a – 4 ) (b – 2 ) (c – 3)?
IfΒ Β a 2Β + b 2Β + c 2Β = 40 & ab + bc + ca = 12 thenΒ a + b+ c = ?