Question
P and Q individually can complete the work in 38 days
and 57 days respectively. If the time taken by R alone to complete the work is 1.25 times the time taken by P and Q together to complete the work, find the time taken by R to complete the work while working alone.Solution
Time taken by P and Q together to complete the work = (38 × 57)/ (38 + 57) = 22.8 days Time taken by R alone to complete the work = 1.25 × 22.8 = 28.5 days
A device that helps to prevent congestion and data collision?
Which type of memory can be both read from and written to by the processor?
State true/false
Trojan works in background and steal data which is sensitive
In the context of backups, what is a retention policy?
Which property distinguishes a B+ tree from a B-tree?
Which network topology requires the highest amount of cabling?
Which of the following is lowest in memory hierarchy?
Which network layer protocol is responsible for multicasting, where a packet is sent to multiple destinations simultaneously?
What is a blockchain?
In which protocol of email the changes made on one device will not be replicated on other?