Question
In a bag, there are four different colour of balls
namely Red, Blue, Green and Yellow. The ratio between the number of blue and yellow balls in the bag is 3:5 respectively. The number of green balls in the bag is 2.4 times the number of blue balls in the bag. The average of the number of Red, Blue, Green and Yellow balls in the bag is 25. If the probability of picking two Red balls from the bag is (46/825), then find out the probability of picking two balls from the bag such that none of them is Red and Yellow.Solution
The ratio between the number of blue and yellow balls in the bag is 3:5 respectively. Letβs assume the number of blue and yellow balls in the bag is β3aβ and β5aβ respectively. The number of green balls in the bag is 2.4 times the number of blue balls in the bag. number of green balls in the bag = 2.4x3a = 7.2a The average of the number of Red, Blue, Green and Yellow balls in the bag is 25. number of Red, Blue, Green and Yellow balls in the bag = 25x4 = 100 number of Red balls in the bag = 100-(3a+5a+7.2a) = (100-15.2a) If the probability of picking two red balls from the bag is (46/825). [(100-15.2a)x(99-15.2a)]/(100x99) = (46/825) [(100-15.2a)x(99-15.2a)]/(4x3) = 46 [(100-15.2a)x(99-15.2a)] = 46x12 [(100-15.2a)x(99-15.2a)] = 24x23 So (100-15.2a) = 24 15.2a = 100-24 a = 5 Similarly (99-15.2a) = 23 a = 5 Number of Blue and Green balls in the bag = (7.2a+3a) = 10.2a = 10.2x5 = 51 Probability of picking two balls from the bag such that none of them is Red and Yellow = (51x50)/(100x99) = (17)/(2x33) = 17/66
Karan, Arjun and Krunal alone can complete a work in 35, 70 and 60 days respectively. All of them started working together but after 3 days from start K...
20 boys can dig a pit in 15 days, while 5 men can dig the same pit in 6 days. In how many days will 10 boys and 1 man together dig the pit?
- If Neha can complete a work in 40 days by working 5 hours a day, how many hours per day should she work to complete the same work in 25 days?
Mira is 40% more efficient than Priya, and Neha is 10% more efficient than Mira. If Neha and Mira together can do a piece of work in 15 days, in how man...
25 men can finish a work in 8 days by working 9 hours a day. How many more men are needed to finish the work in 10 days by working 6 hours a day?
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
40 men can complete a piece of work in 48 days. βxβ men started the work and after 33 days 64 more men joined them so that whole work was finished i...
Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start K...
Efficiency of A, and B are in the ratio of 3 : 4. If both can do a work together in 30 days. Find out how much days A will take to complete the work alone?
40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the s...