Question
Three workers A, B and C, can complete a task in 15, 18 and 28 days, respectively. If they all work together, how long will it take to complete the task (rounded off to two decimal places)?
More Previous year papers Questions
- The cost price of an article is Rs. x. It is marked up by 100 percent and it is sold at Rs. 420 after giving 30 percent discount. What is the value of x (i...
- The average monthly expenditure of a family was ₹10,000 during the first three months, ₹12,500 during the next four months, and ₹13,500 during the last fiv...
- A six-digit number 11p9q4 is divisible by 24. Then the greatest possible value for pq is:
- A car travels a distance of x km at speed of 5(5/9) m/sec and returns at 5 m/sec to the starting point. If the total time taken by the car is 7(3/5) hours....
- A cylindrical oil tank has a radius of 5 m and a total surface area of 628 m², what would be its curved surface area? (round off to the second decimal plac...
- The LCM of two numbers is 660 and their HCF is 5. If one of the numbers is 55, find the other.
- If the radius of a circle becomes 15 times, then how much of its circumference will be the previous perimeter?
- If the radius of a circle is decreased by 15%. by what percent area of the circle decreases?
- The breadth ‘b’ of a room is twice its height and half of its length. Find the length of the longest diagonal of the room.
- Find the area of a square, one of whose diagonals is 4.8 m long.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt