      Question

      Amit can finish a work in 4 days and Sumit can do the

      same work in 6 days. If they work together, then the work will be finished in how many days?
      A 4(2/5) Correct Answer Incorrect Answer
      B 2 Correct Answer Incorrect Answer
      C 2(2/5) Correct Answer Incorrect Answer
      D 5 Correct Answer Incorrect Answer

      Solution

      The correct answer is C