Question
100 workers working 8 hours a day can dig a canal 2000
metres long in 25 days. Find the number of workers required to dig a similar canal of 2800 metres long in 32 days working 5 hours a day.Solution
 the total man-hours for the first canal= 100 workers × 8 hours/day × 25 days = 20000 man-hours For 2000 meters, rate = 20000 man-hours/ 2000 meters = 10 man-hours per meter. the total man-hours for the second canal= 2800 meters × 10 man-hours/meter  = 28000 man-hours Find the number of workers required- W x 5 hours/day × 32 days = 28000 man-hours 160W= 28000 W =28000/160 W=175
What is the maximum subsidy amount for individual units under PMFME?
What feature of the "Flash Pay" RuPay smart key chain launched by Federal Bank emphasizes enhanced security for contactless payments?
Who is roped as the brand ambassador of PharmEasy?
Who among the following replaced Morarji Desai as the Prime Minister of India in 1979?
Who won the 2023 Superbet Rapid & Blitz Poland, the second leg of the Grand Chess Tour?
Where are the headquarters of the Centre for Development of Advanced Computing?
Who is the author of the book "The Rajiv I Knew," which delves into Rajiv Gandhi's accords with insurgents and the controversies that marked his tenure?
Which of the following term means using shares as collateral and taking a loan against them?
Who is the chairperson of the National Statistical Office?
Which bank has launched UPI integration for NRE clients through its mobile banking platform enabling NRIs to seamlessly utilise UPI features through the...