Question
100 workers working 8 hours a day can dig a canal 2000
metres long in 25 days. Find the number of workers required to dig a similar canal of 2800 metres long in 32 days working 5 hours a day.Solution
 the total man-hours for the first canal= 100 workers × 8 hours/day × 25 days = 20000 man-hours For 2000 meters, rate = 20000 man-hours/ 2000 meters = 10 man-hours per meter. the total man-hours for the second canal= 2800 meters × 10 man-hours/meter  = 28000 man-hours Find the number of workers required- W x 5 hours/day × 32 days = 28000 man-hours 160W= 28000 W =28000/160 W=175
 Who has the power to constitute the National Company Law Tribunal?
Which of the following actions by a service provider would constitute "deficiency" under Section 2(11) of the Consumer Protection Act, 2019?Â
A is tried for the murder of B by beating him with a club with the intention of causing his death.
Which of the following is a relevant fact?
Which of the following describes the effect of the 44th Amendment (1978) of the Constitution on property and emergency provisions?
Article 2 of the Constitution of India (As amended) states. Parliament may by law ________ new states on such terms and conditions as it thinks fit.
Section 72A penalises which of the following?Â
Doctrine of Res gestae is an exception to?
S. 32 of the Indian Evidence act covers:
Under the Income Tax Act, 1961, which of the following incomes is fully exempt from tax in the hands of the individual taxpayer?
What does the term "Vis Major" refer to?