the total man-hours for the first canal= 100 workers × 8 hours/day × 25 days = 20000 man-hours For 2000 meters, rate = 20000 man-hours/ 2000 meters = 10 man-hours per meter. the total man-hours for the second canal= 2800 meters × 10 man-hours/meter = 28000 man-hours Find the number of workers required- W x 5 hours/day × 32 days = 28000 man-hours 160W= 28000 W =28000/160 W=175