    If Mohit can complete 2/3rd of a work in 24 days, then

    in how many days can 1/9th of the work be completed by him?
    A 8 Correct Answer Incorrect Answer
    B 4 Correct Answer Incorrect Answer
    C 6 Correct Answer Incorrect Answer
    D 5 Correct Answer Incorrect Answer

    Solution

    Let the time taken be x, According to question, M x 24/2/3 = M x x/1/9 Mx 24 x 3/2 = M × x × 9 24 x 3/2 = x × 9 12 x 3 = x x 9  x = 4 days