Question
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
More Previous year papers Questions
- The diameter of a cycle wheel is 28 cm. How many revolutions will it make in moving 13.2 km?
- If p cos A = 2q sin A and 2p cosec A – q sec A = 3, then the value of p² + 4q² is:
- Which is the smallest 5 – digit number that is divisible by each of 54, 120 and 96?
- Abhinav bought some pencils for ₹ X. He sold 20% of pencils at 25% loss, one third at 20% profit and the remaining at 25% profit. If the total profit earne...
- The price of a variety of a commodity is 7/kg and that of another is 12/kg. Find the ratio in which two varieties should be mixed so that the price of the ...
- Suresh, Dinesh and Ramesh became partners in a business by investing money in the ratio of 3 : 6 : 8. If their investments is increased by 5%, 15% and 20%,...
- Question 7
- At what rate per cent per annum will a sum of 15,625 amount to 21,952 in three years, if the interest is compounded annually?
- A bank charges simple interest for Rs. K at the rate of r1/2 for n² years. Another bank charges simple interest for Rs.L at the rate of r3/2 for n³ years ...
- Two circles having radii 12 cm and 8 cm, respectively, touch each other externally. A common tangent is drawn to these circles which touch the circles at M...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)