Question
To do a certain work, the ratio of the efficiencies of
A, B and C is 3:5.8. Working together, they can complete the same work in 15 days. If only A and B work together for 12 days and leave, and then C comes to complete the remaining work, for how many days will C work?Solution
According to the question Time taken by A, B, and C together to complete the same work = [15 x (3 + 5 + 8)] units = (15 x 16) units = 240 units Time taken by A and B together = [(3 + 5) x 12] = (8 x 12) units = 96 units The remaining work = (240-96) units = 144 units Now, Time taken by C to complete the remaining work = (144/8) days = 18 days The required time taken by C to complete the remaining work is 18 days.
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- Pipes X and Y can fill a water tank individually in 24 minutes and 36 minutes, respectively. A third pipe Z can empty the tank in 72 minutes. If all three ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves....
The ratio of time taken by P, Q and R to complete work alone is 4:6:3 respectively. If all three together complete the work in 8 days, then find in how ...
18 women can do piece of work in 12 days. 12 men can do the same piece of work in 9 days. Find in how many days will 8 men and 8 women complete that work?
A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for...