      Question

      Working 2 hours per day, R1 alone can complete a work

      in 6 days. Working 5 hours per day, R2 alone can complete the same work in 4 days. Working 3 hours per day, in how many days both R1 and R2 together can complete the same work?
      A 5 days Correct Answer Incorrect Answer
      B 2.5 days Correct Answer Incorrect Answer
      C 7 days Correct Answer Incorrect Answer
      D 3.5 days Correct Answer Incorrect Answer

      Solution

      Total hours are taken by R1 = 2 x 6 = 12 hours Total hours taken by R2 = 5 x 4 = 20 hours Let, m = time taken in hours by R1 and R2 β‡’ 1/12 + 1/20 = 1/m 8m = 60 m = 60/8 hours Time taken in days if R1 and R2 works 3 hours a day = 60/(8Β  x 3) = 60/24 = 2.5 days