Question

A and B do a work in 15 days and 25 days, respectively. They worked together for 5 days, after which B replaced by C and the remaining work was completed by A and C in the next 4 days. In how many days will C alone complete the same work?

A 24 days
B 20 days
C 15 days
D 25 days