Question
A certain number of persons can complete a piece of work
in 46 days. If there were 8 persons more, the work could be finished in 16 days less. How many persons were originally there?Solution
Let there be x men originally x men finish the work = 46 days And (x + 8) persons finish the work = (46-16) = 30 days  x men finish the work = 46  1 man finish the work = 46x  (x + 8) persons finish the work = 30 1 man finish the work = 30(x + 8) Now, 46x = 30(x + 8)  46x = 30x + 240 16x = 240 x = 15 There were 15 persons.
Which one of these online marketplaces becomes the first major platform to offer direct mutual funds to consumers?
Select the wrong statement regarding Veer Chandra Singh Garhwali Self-Employment Project--
What is the financial outlay approved by the Union Cabinet for the continuation of PM-AASHA schemes until 2025-26?
Who was the first Chief Commissioner of Chandigarh?
DU PONT Analysis deals with:
What was India’s rank in the 2024 Global Nature Conservation Index (NCI), and what was its score?
Cairn Energy Co. is headquartered in which country?
Where is the Kodaikanal Solar Observatory situated?
When did the British Government call the Indian leaders for the first Round Table Conference?
On which date has the United Nations designated as World Football Day?