A certain number of persons can complete a piece of work
in 46 days. If there were 8 persons more, the work could be finished in 16 days less. How many persons were originally there?Solution
Let there be x men originally x men finish the work = 46 days And (x + 8) persons finish the work = (46-16) = 30 days x men finish the work = 46 1 man finish the work = 46x (x + 8) persons finish the work = 30 1 man finish the work = 30(x + 8) Now, 46x = 30(x + 8) 46x = 30x + 240 16x = 240 x = 15 There were 15 persons.
What does resolution plan mean?
Which of the following is correct about altering the boundaries of any State?
Which of the following is an exception to S.132?
Under the Industrial Disputes Act, 1947, Section 2A deems a dispute as "Industrial Dispute" automatically if:
Under the SARFAESI Act, 2002, the "Secured Creditor" refers to:
How may a conciliator communicate with the parties in a conciliation process?
Under Section 2(ac) of the Securities Contracts (Regulation) Act, 1956, which of the following is EXCLUDED from the definition of "Derivatives"?
The mortgagor ostensibly sells the mortgaged property in-
Section 221 provides that for offences under Section 67 BNSS where the parties are married—
According to Sale of Goods Act, 1930 “goods”